| Implementation Cycle |
|
The LIMS installation is divided in System installation and System configuration. During the system installation we install and configure the database, install all of the applications on the server, configure client workstations and setup the instrument interfacing. The system installation includes the installation training and documentation for IS personnel. This task is usually finished in 3 days.
Once the system is installed, configuration begins. This is when the LIMS is customized through various configuration options to conform to the labs requirements. All users, clients records, test parameters and invoicing information are entered into the system. If migrating from an existing LIMS or similar system, historical data can be imported to the LIMS.
Once the LIMS configuration is finished, staff are trained and the system begins a trial run. Further adjustments and modifications can be made if required. A medium size lab should be able to begin the second week with an 70% operable LIMS system.
Installation steps
Network review (Ensure capacity available and rectify if necessary)
New computers if required
Server Setup, data base & OS
Install OnWSH and additional components
Procurement of hardware to facilitate instrument connectivity
Obtain List of methods operating on the Lab
Train the Trainers
Configure methods, and validate
Configure Instruments
Custom Interface( Option to connect to third party software)
Custom features identified, and implemented (possible custom code)
Custom Instrument driver
Hand holding for training at the work bench
Reporting requirements ( Online weakness- write reports in Crystal or install a copy o f Crystal)
Application installation
Network and client computer configuration
Instrument interfacing
Configuration stepsDatabase configuration
Method library definition, sample templates
Client, cost and other static data
Migration of historical data
Report formats
Worksheet templates
Report templates
|